Update: BCUC Section 5 Transmission Inquiry - On Hold
On Friday, the BCUC notified intervenors that all future scheduled workshops and regional sessions for the Section 5 Transmission Inquiry were postponed pending further notification. Here is a copy of the BCUC's notice.
Today, the Vancouver Sun reported that the temporary halt to the 7 month old transmission inquiry is believed to be based on the government's desire to properly align its interests with those of BC Hydro and BCTC on matters relating to the development and export of green power in the province and the recent rulings made by the BCUC.
The Inquiry has encountered lengthy delays for a number of reasons, including as a result of delays in the provision of key evidence, by important first nations consultation issues and more recently, by an intervenor proposal that would see a first nations advisory panel being formed.
Obviously, stay tuned, there is much more to come on this.